Installation Over Wall Openings

If not properly flashed, all masonry wall openings possess a potential moisture problem. In brick veneer systems there are two distinct methods for properly installing the flashing membrane, as shown in Figures 1 & 2. In Figure 1 the flashing membrane* is turned up at the ends and placed inside the head joint, forming a dam. This acts as a directional aid, guiding water through the weep holes to the exterior surface of the wall.

 In Figure 2 a self adhesive preformed end dam is placed under the flashing membrane. (shown on top of flashing in the drawing for clarity).

Figure 1

Figure 2

Figures 3 & 4 show the complex detail required to properly flash a brick veneer bay window. Preformed end dams are used in a stair-step fashion, culminating with a flashing tray and weep hole to direct collected water out of harms way.

Figure3:

Figure 4:

Preformed self-adhesive corners are also available for baseflashing as shown in Figure 5.