TOP302
folderedge.jpg
CMU Installed Costs
folderbar.jpg

[HOME] [TECH LIBRARY] [Masonry Estimating] [COST GUIDE] [CMU Cost]

 

 

masonry wall cost guide - cost of brick - cost of block - cost of stone

2007 Masonry Cost Guide

Installed Cost of Concrete Block Walls - CMU - Concrete Masonry

 

Click on a wall to continue

15

4" CMU (average productivity)

15a

4" cmu (high productivity)

15b

4" cmu (low productivity)

15c

4"CMU partition (2 sides exposed)

16

4" split face CMU (integral water repellent)

17

4" ground face CMU

18

4" glazed CMU

18b

2" glazed CMU

26

6" CMU

27

6" Split face CMU (Integral Water Repellent)

28

6" Ground Face CMU

29

6" Glazed CMU

31

6" bond beam (cost per lf) (8X16 FACE)

33

8" Concrete Block (115 PCF density) (average productivity)

33a

8" Concrete Block (115 PCF density) (high productivity)

33b

8" Concrete Block (115 PCF density) (low productivity)

34

8" Lightweight CMU (100 PCF) (average productivity)

34a

8" Lightweight CMU (100 PCF) (high productivity)

34b

8" Lightweight CMU (100 PCF) (low productivity)

34c

8"x8"x24" lighweight CMU (avg. productivity)

34d

8"x8"x24" lighweight CMU (high productivity)

35

8" Glazed CMU

36

8" Split Face CMU (integral water repellent) (average productivity)

36a

8" Split Face CMU (integral water repellent) (high productivity)

36b

8" Split Face CMU (integral water repellent) (low productivity)

37

8" Ground Face CMU

39

8" bond beam (cost per lf) (8X16 FACE)

43

10" CMU 115 PCF Density (average productivity)

43a

10" CMU 115 PCF Density (high productivity)

43b

10" CMU 115 PCF Density (low productivity)

44

10" Split face CMU (integral water repellent) (average prod.)

44a

10" Split face CMU (integral water repellent) (high productivity)

44b

10" Split face CMU (integral water repellent) (low productivity)

45

10" Ground Face CMU

46

10" Glazed CMU

48

10" bond beam (cost per lf)(8X16 FACE)

53

12" CMU 115 PCF Density

53a

12" CMU 115 PCF Density with perlite insulation (Rw=7.9)

53b

12" CMU 115 PCF Density with foamed insulation (Rw=10)

54

12" Lightweight CMU 100 PCF Density (average productivity)

54a

12" Lightweight CMU 100 PCF Density (high productivity)

54b

12" Lightweight CMU 100 PCF Density (low productivity)

55

12" Split Face CMU (Integral Water Repellent)

55a

12" Split face with foamed in insulation (Rw=10)

55b

12" Split Face + 1.5" polyisocyanurate insulation inside

55c

12" Lightweight Split Face CMU (Integral Water Repellent)

57

12" Glazed CMU

65

12" bond beam (cost per lf) (8X16 FACE)

PLEASE READ THE FOLLOWING BEFORE VIEWING ESTIMATES

Union Mason Contractors in 32 counties of North and Central Illinois and Northwest Indiana were surveyed to obtain the cost information that follows. More than 69 commonly used masonry wall types, plus masonry paving applications, are shown. There is literally an infinite possibility of combinations of materials for most wall thicknesses. Cost figures as shown on the following pages are based on:

  1. Labor and materials costs as of June. 1, 2006 - May 31, 2007
  2. Composite walls are wire tied.
  3. All masonry units laid in running bond.
  4. Wall sections estimated are 10' by 10' without openings, piers,  off-sets or corners. (walls with numerous
  5. openings, piers and off-sets will increase square foot costs)
  6. All flashing, weep holes, movement joints, wall ties, cleaning and striking are all included

The cost figures shown in this booklet should be used for informational and educational purposes only, not for estimating masonry work. These figures are not to be viewed as actual prices for masonry construction in the Midwest area. Specific masonry wall costs are determined by a mason contractor and must, of course, be based upon actual plans, specifications, site conditions and season of construction.